SUPREME
COURT TAKES A SERIOUS VIEW ON TEHRI OUSTEES
The long pending Tehri HEP case was again heard in
Supreme Court by Justice H.L. Ghokhle, Justice Kurian Joseph bench.
It must be remembered that on 29th July 2005,
all the divergent tunnels were closed and tehri dam reservoir started
filling to its capacity but till now rehabilitation had not been
completed. Environmental conditions were not kept in mind while
constructing the dam infrastructure. Bridges that used to connect
villages on two sides of the river have not yet been constructed
which have increased distances to a large extent resulting in extreme
problems of commutation for villagers. Corruption on rehabilitation
issues have grown higher and higher with time. Grievance redressal
mechanism has not been allowed to function properly due to various
technical reasons.
Till now, land rights not been given to old oustees who
were rehabilitated due to Tehri HEP and situation of the provision of
civic amenities is also in bad conditions
N.D. Juyal and Shekhar Singh challenged the Nainital
High Court verdict dated 29th July 2005 which had allowed
Tehri Hydro Development Corporation (THDC) to close the tunnel to
fill the reservoir. Battle is going on in the Supreme Court and it
has proved that rehabilitation of this project has not yet been
completed. So the order of 29th July 2005 High Court was
proven wrong.
Supreme Court looked in to the matter with deep concern
and did not allow THDC to fill the reservoir fully. Even state
government did not give clearance to THDC to fill the reservoir. The
new problem that has arose is the issue of 80 villages in the
vicinity of Tehri dam which are now on the risk of subversion and
landslides. Life of these villagers have become miserable and they
deserve rehabilitation because their villages are not anymore in the
condition to live. For them THDC and government has planned to come
up with a new collateral policy. The tussle between the THDC and
state government is going on because State Government wants to
rehabilitate new oustees in Haridwar and Dehradun district. On the
other hand THDC is putting pressure to rehabilitate around the
reservoir itself.
The petitioner, represented by Advocate Sanjay Parikh
pleaded that there is no need of any collateral policy because these
people are also affected due to the same Tehri dam so these oustees
should get rehabilitation under the same policy as for the earlier
ones. And they should be rehabilitated in Haridwar, Dehradun area
with full civic amenities, land rights and cultivable land which were
promised to the old oustees as their rights but were never fulfilled.
Advocate Sanjay Parikh pleaded that this is our main focus and we’ve
filed other issues like bridges, command area plan, catchment area
treatment plan etc. that should be heard by the court. The point that
this area is environmentally fragile also needs to be understood.
This shall allow formulation of better rehabilitation policies for
the people. Justice Ghokhle very humanely, said that our first motto
is to give land to the people who were displaced.
He further gave reference of the Supreme Court order
dated 1 Sept 2003, “It is made clear that the condition of
pari-passu implementation of conditions prior to the commissioning of
the project shall be closely monitored under the existing mechanism
set up by MoEF and the project authorities will ensure that prior to
closing of diversion tunnels T1/T2 for impoundment of the reservoir,
evacuation, resettlement and rehabilitation are completed in all
respects.” Which was not done. In Narmada and other cases, dam
got constructed but rehabilitation promises and schemes were never
implemented. There were many cases regarding that in SC which puts
burden on the court too apart from all the miseries that the people
have to face at the cost of pseudo development of our country.
Advocate Parikh said that question is not only below 830 mts (the
height of the reservoir from the sea level) but also about villages
around the reservoir which are sinking as they are also directly
affected.
Senior council Mr. Gonsalves supporte the arguments. Ms.
Rachana Shrivastava, learned counsel appearing for the State of
Uttarakhand submits that the State is of the view that the affected
families should be rehabilitated downstream because the upper-region
is fragile. According to the State Government the number of such
families is 414. The State Government has identified the land in
Khanpur area of District Haridwar and it is also proposing to find
out appropriate land in District Dehradun.
Mr. Raval, learned senior counsel appearing for the
Tehri Hydro Development Corporation on the other hand submits that
rehabilitation should be upstream and not downstream. Ms. Shrivastava
submits that a proposal has been submitted to the Ministry of
Environment and Forest and it is awaiting clearance from them.
Mr. H.P. Rawal also said that we should also be allowed to
file our issues to Ministry of Environment and Forest Ministry
otherwise the issue will not be dealt with effectively.
The Supreme Court expects the Central Government to take
a decision thereon as expeditiously as possible and if possible,
report further development to this Court by the next date of hearing
that is scheduled to be on 4th March, 2014.
So tussle is going on and oustees are waiting for mere
rehabilitation, at the very least. NO DAM SUPPORTERS ARE SAYING ANY
THING ON THIS ISSUE AS THEY ARE BUSY LOBBYING FOR NEW DAMS PROJECTS.
Vimalbhai and Puran Singh Rana
“The natural resources of a country are the sovereign property of its people. They are not ours to steal or exploit in the name of our comfort, our corporations, or our consumerism. The Third World is not a world apart.”
ReplyDeleteAbove is the view of the Speaker at the Kimberly summit.
Sometimes I think that I am living in fourth or fifth world, because our Godfathers "THDC, State & Central Govt" are too far from a civilized world. They constructed a dam for my betterment which destructed my village, my life and thousands of others. They made me to re-settle myself without a penny of compensation. Now they are fighting with each other to decide where I must live. They may take another 50-100 years to decide because they are not affected at all.
Who is guilty? My heritage and no one else. They never predicted that after 400-500 years a Govt will decide to construct a dam here to produce electricity and make us homeless in a endless dark.