NOTICE
ISSUE BY NGT: COMPENSATE THE LOSS TO SRINAGAR HOUSEHOLD
Notice
issued to Alaknanda
Hydropower Co. Ltd.,
Central Ministry of
Environment
and
Forests and Uttarakhand
State Government by National Green Tribunal on 9th
January, 2014. (NGT order is attached)
On
2nd
January, 2014, Srinagar
Bandh Aapda Sangharsh Samiti
through its Vice president Shri
Premballabh Kala and
Vimal Bhai,
Convenor, Matu
Jansangthan filed
a case in NGT for the compensation of damage caused due to Srinagar
Hydro Electric Project. Applicants
seeking restoration, damage and com National
Green Tribunal pensation
against the project proponent of the Srinagar Hydroelectric Project
(330 MW) who are responsible largely for the devastation caused to
the Shaktibihar, Lower
Bhaktiana, Chauhan Mohalla, Gas Godown, Food Godown, SSB, ITI, Resham
Farm, Roadways Bus Stand, Nursery Road, Alkeshwar Temple, Gram Sabha
Ufalda’s Fatehpur reti, Sriyantra Island Resort, and other places
including Governmental / Quasi-Governmental/Personal and public
property of Srinagar in
Pauri
district
of
Uttarakhand.
Counsel
Rahul Choudhary on behalf of applicants argued that
the project proponent has dumped large quantity of muck generated
from the construction of the Srinagar Hydroelectric Project just
beside the gates of the dam on the river bed of Alaknanda. On 16th
& 17.06.2013 because of the heavy rain and floods the water was
filled in the reservoir of the Srinagar Hydroelectric Project and the
project proponent kept the gates of the dam close which led to
accumulation of water and creating huge reservoir. The project
proponent then opened the gate which resulted in massive flow of
water suddenly which also swept away the muck dump on the river bed
and all the muck then along with the water reached the villagers and
filled up the house and various other areas and contributed in large
scale to the damaged. The project proponent has not even constructed
retention wall which resulted in further damage because of the dam.
After listening the
counsel the bench of
five members issued the notice to all the respondents. Next
hearing is scheduled on 6th
February.
It
is well known that after 6 months of June 2013 calamity, there has
been no inquiry set up by the state or central government. We have
been trying to file a FIR but local district police official have
always refused to do so. Not even a single dam supporter including
local MPs and MLAs cared to reach people through any means. It is
very much clear that the dam supporters are supporting dams not for
the welfare of people but for their own personal interest.
After
the June calamity, 2013 Mat Jansangathan had done the ground survey
and it can be safely deduced that underconsturction and working dams
raised the quantum of the calamity. We raised this issues with the
masses thtough leaf letting, meetings, press confencess,etc. We sent
letters to authorities, different ministries, Chief Minister of
Uttarakhand, MLAs and MP's but no one showed any interest in the
issue. Now we entered into legal battle too. This
is the first ever case filed in any court for the compensations for
the loss of people's assets.
We
will use all means under the Constitution of India to take our
rights.
Puran
Singh Rana
(Matu
Jansangthan)
Chndra Mohan Bhatt
Vijay Laxmi Ratudi
(Srinagar
Bandh Aapda Sangharsh Samiti)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------------
-------------------------------------------------------------------------------------------------------------------------------------------------------------------------
NGT ORDER
http://www.greentribunal.gov.in/date-wise-order.php
BEFORE THE NATIONAL GREEN TRIBUNAL,
PRINCIPAL BENCH, NEW DELHI
M.A. NO. 7 OF 2014 & M.A. NO. 8 OF
2014
IN
Original Application No. 3 of 2014
Srinagar Bandh Aapda Sangharsh Samiti &
Anr.
Vs.
Alaknanda Hydropower Co. Ltd. &
Ors.
CORAM : HON’BLE
MR. JUSTICE SW
ATANTER KUMAR, CHAIRPERSON
HON’BLE
MR. JUSTICE U.D.
SALVI, JUDICIAL MEMBER
HON’BLE
MR. DR. D.K. AGRAW
AL, EXPERT MEMBER
HON’BLE
MR. B.S. SAJW AN,
EXPERT MEMBER
HON’BLE
DR. R.C. TRIVEDI,
EXPERT MEMBER
Present: Applicant:
Mr. Rahul
Choudhary, Advocate
Respondents:
None
appeared
Date and
Remarks
Item No. 12
January 9, 2014
Orders of the Tribunal
We have heard the Learned counsel
appearing for
the Applicant.
Issue Notice to the Respondents by
registered
post/acknowledgement due and Dasti as well.
Notice returnable on 06th February,
2014.
Notice on Misc. Applications as well.
Requisites to be filed within three
days from today.
Learned counsel appearing for the
Respondent 2
puts in appearance and prays for time to file the
Reply.
Let the Reply be filed within two weeks
from today with
advance copy to the Learned counsel appearing for
the
Applicant who may file Rejoinder thereto, if any, within
one
week thereafter.
........................................,CP
(Swatanter Kumar)
........................................,JM
(U.D. Salvi)
.........................................,EM
(Dr. D.K. Agrawal)
.........................................,EM
(B.S. Sajwan)
.........................................,EM
(Dr. R.C. Trivedi)
No comments: